One month on: El Teniente at about 60% of its usual production rate, US$340m impact estimated
As of 2026-10-08 · Observation periods are shown separately.
2025-08-31 · One month on: El Teniente at about 60% of its usual production rate, US$340m impact estimated · Direction: Higher
Disclosed facts
Swipe horizontally to see the full table.
| Assertion | Disclosure |
|---|---|
| Status at disclosure | Codelco said the production rate was around 60% of the usual. |
| Operational scope | Recursos Norte and Andesita stayed stopped as the zones most damaged in the accident. |
| Operating change | Codelco's release, issued one month after the accident, states that six workers died in it. |
Disclosure boundary
The time unit of the ore figure (per day?) is not stated; there is no copper tonnage or full-year 2025 loss estimate; the US$ figure is economic, not tonnes.
Status at disclosure
Status as disclosed on this date
Source
Related project
El TenienteSource: metalsgowhere.com, as of 2026-10-08. Citation & data use