SimFer · Simandou supply ramp-up
As of 2026-10-08 · Observation periods are shown separately.
2026-07-15 · SimFer · Simandou supply ramp-up · Direction: Higher
Disclosed facts
Swipe horizontally to see the full table.
| Assertion | Disclosure |
|---|---|
| Plan or guidance | SimFer 2026 sales guidance was 5–10 million tonnes and covered Simandou Blocks 3 and 4 only. |
| Status at disclosure | Mine and port construction were more than three quarters complete; full rail commissioning occurred in Q1. |
Disclosure boundary
SimFer Blocks 3 & 4 only; planned sales, not delivered volume or all-Simandou capacity.
Status at disclosure
Plan / progress at disclosure
Source
One or more linked sources in this table lack a page anchor; no page number was inferred.
Source: metalsgowhere.com, as of 2026-10-08. Citation & data use