METALSGOWHERE ATLAS · SUPPLY RESEARCH
Las Bambas precautionary suspension, 18–21 August 2026
As of 2026-08-19 · Observation periods are shown separately.
Whole-mine stop for three days after a fatal incident; the company did not quantify lost output. Loss here is the 2025 daily rate times three days.
- Metal
- Copper
- Side
- Mine
- Country
- PE
- Period
- 2026-08-18 → 2026-08-21
- Status
- Resumed
- Quantity basis
- Estimated mine-production loss
- Production basis
- 410.8 kt / yr · MetalsGoWhere Atlas: Las Bambas 2025 full-year production, copper in concentrate, 100% basis
- Affected share
- 100%
- Estimated daily impact
- 1,126 t/day
- Project page
- las-bambas
Sources
- MMG · Company or regulator document · 2026-08-19
Source: metalsgowhere.com, as of 2026-08-19. Citation & data use