Grouped by production stage. Periods, products and scopes differ between projects, so entries are not a ranking and should not be added up.
Nickel iron
Indonesia · Nickel iron · Single site
Operator: Nickel Industries / Angel Nickel · ANI
Production: Not disclosed · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in NPI · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Standalone CY2025 production unverified; the annual report discloses 124,966 t Ni for four plants combined. Sales cannot substitute for output.
New Caledonia · Nickel iron
Operator: Société Le Nickel / Eramet
Production: 36,300 t · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel contained in ferronickel · 100% project basis
Source: Eramet · 2025 Full-Year Results · 2026-02-18
SLN ferronickel production at Doniambo is 36.3 kt-Ni in 2025; not added to upstream ore production.
Indonesia · Nickel iron · Single site
Operator: Nickel Industries / Hengjaya Nickel · HNI
Production: Not disclosed · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in NPI · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Standalone CY2025 production unverified; the annual report discloses 124,966 t Ni for four plants combined. Sales cannot substitute for output.
China · Nickel iron · Single site
Operator: Lygend Resources
Nameplate capacity: 18,000 t/year · Period: Not disclosed · Basis: Nickel content in ferronickel · 100% project basis
Source: Lygend Resources 2025 Annual Report · 2026-04-30
Nickel-metal tonnes, not gross ferronickel product mass.
Indonesia · Nickel iron · Operating system
Operator: Nickel Industries
Production: 124,966 t · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in NPI · Operating-system scope
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Combined HNI/RNI/ANI/ONI output; 125,341 t sales are not production. Not summed with individual plants.
Brazil · Nickel iron
Operator: Vale Base Metals
Production: 26,000 t · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel contained in ferronickel · 100% project basis
Source: Vale Base Metals · 2025 资产手册 (Chinese) · 2026-03-30
2025 Ni in ferronickel: 26 kt. Expanded nameplate of 40 kt/year is not an annual target.
Indonesia · Nickel iron · Single site
Operator: Nickel Industries / Oracle Nickel · ONI
Production: Not disclosed · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in NPI · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Standalone CY2025 production unverified; the annual report discloses 124,966 t Ni for four plants combined. Sales cannot substitute for output.
Indonesia · Nickel iron · Single site
Operator: Nickel Industries / Ranger Nickel · RNI
Production: Not disclosed · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in NPI · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Standalone CY2025 production unverified; the annual report discloses 124,966 t Ni for four plants combined. Sales cannot substitute for output.
Korea, Republic of · Nickel iron · Single site
Operator: SMSP / POSCO
Nameplate capacity: 54,000 t/year · Period: Not disclosed · Basis: Nickel content in ferronickel · 100% project basis
Source: SMSP: SNNC Gwangyang ferronickel plant
Page describes the 2015 expansion; another 45 kt statement has an unclear product basis. Uses explicit contained-Ni capacity, with effective date unverified; not CY2025 output.
Indonesia · Nickel iron
Operator: PT Weda Bay Nickel
Production: 35,800 t · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel contained in ferronickel · 100% project basis
Source: Eramet · 2025 Full-Year Results · 2026-02-18
PT WBN NPI plant production is 35.8 kt-Ni on a 100% basis. Wet ore tonnes, 43% offtake sales and equity interests are excluded.
Intermediates
Indonesia · Intermediates · Single site
Operator: Huayou / Tsingshan
Nameplate capacity: 120,000 t/year · Period: Not disclosed · Basis: Nickel content in MHP · 100% project basis
Source: Huayou: Huafei reaches design capacity · 2024-04-09
Disclosure gives March 2024 only; no exact ramp-up day is invented. Standalone CY2025 actual output unverified.
Indonesia · Intermediates · Single site
Operator: Huayou / Tsingshan / Nickel Industries
Production: 85,031 t · Period: 2025-01-01 — 2025-12-31 · Basis: Nickel content in MHP · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Nameplate capacity: 60,000 t/year · Period: Not disclosed · Basis: Nickel content in MHP · 100% project basis
Source: Nickel Industries 2025 Annual Report · 2026-04-24
Full-project output; NIC attributable 10% output of 8,503 t is not the project total.
Indonesia · Intermediates · Operating system
Operator: Lygend / Harita
Nameplate capacity: 120,000 t/year · Period: Not disclosed · Basis: Nickel content in MHP · Operating-system scope
Source: Lygend Resources 2025 Annual Report · 2026-04-30
Six HPL/ONC lines combined; 14,250 t cobalt is separate and not added to nickel.
Papua New Guinea · Intermediates
Operator: Ramu JV / MCC
Production: 33,007 t · Period: 2025-01-01 — 2025-12-31 · Basis: intermediate nickel · 100% project basis
Source: Nickel 28 · Ramu 2025 Operating Performance · 2026-02-23
Full-project annual nickel contained in MHP: 33,007 t. Primary JV shareholder disclosure; neither 8.56% equity output nor gross MHP mass.
Indonesia · Intermediates
Operator: PT Vale Indonesia
Production: 72,027 t · Period: 2025-01-01 — 2025-12-31 · Basis: intermediate nickel · 100% project basis
Source: PT Vale Indonesia · 2025 Results · 2026-03-16
72,027 tonnes of nickel in matte produced in 2025, not gross matte mass or 73,093 tonnes delivered.
Mines
United States · Mines
Operator: Lundin Mining · 2025 reporting period
Production: 9,907 t · Period: 2025-01-01 — 2025-12-31 · Basis: Contained nickel · 100% project basis
Source: Lundin Mining · 2025 Results · 2026-02-19
Calendar-2025 contained nickel, full project. Operator is the 2025 reporting association, not current ownership or status.
Finland · Mines
Operator: Boliden
Production: 11,627 t · Period: 2025-01-01 — 2025-12-31 · Basis: Contained nickel · 100% project basis
Source: Boliden · Kevitsa Mineral Resources and Reserves 2025
11,627 tonnes of nickel in nickel concentrate; not gross concentrate, ore mass or a copper/nickel equivalent.
Canada · Mines
Operator: Glencore
Quantity: Not disclosed · Period: Not disclosed · Basis: Not disclosed · Not disclosed
Source: Glencore · Full Year 2025 Production Report · 2026-01-29
The 2025 report aggregates Sudbury, Raglan and Nikkelverk as INO. Finished nickel from that network is not allocated to the mine.
Canada · Mines · Operating system
Operator: Vale Base Metals
Production: 12,000 t · Period: 2025-01-01 — 2025-12-31 · Basis: Concentrate nickel, Source View · Operating-system scope
Source: Vale Base Metals 2025 Asset Handbook · 2026-03-30
Source View concentrate nickel; not added again to Ontario refined output.
Refined nickel
United Kingdom · Refined nickel · Single site
Operator: Vale Base Metals
Nameplate capacity: 40,000 t/year · Period: Not disclosed · Basis: Refined nickel · 100% project basis
Source: Vale Base Metals 2025 Asset Handbook · 2026-03-30
Approximately 40 kt/year in the source; not CY2025 output.
China · Refined nickel · Operator group
Operator: Jinchuan Group
Nameplate capacity: 190,000 t/year · Period: Not disclosed · Basis: Electrolytic nickel · Operator-group scope
Source: Jinchuan official nickel business profile · 2026-06-29
Group electrolytic-nickel capacity; carbonyl nickel is a separate product, and no group value is assigned to one Jinchang pin.
Australia · Refined nickel
Operator: Glencore
Production: 34,500 t · Period: 2025-01-01 — 2025-12-31 · Basis: Refined nickel · 100% project basis
Source: Glencore · Full Year 2025 Production Report · 2026-01-29
Total refined nickel is 34.5 kt including third-party feed. Own-sourced 32.1 kt is a subset, shown separately and never added.
Norway · Refined nickel
Operator: Glencore
Quantity: Not disclosed · Period: Not disclosed · Basis: Not disclosed · Not disclosed
Source: Glencore · Full Year 2025 Production Report · 2026-01-29
INO total nickel of 101.5 kt covers multiple operations. It is not assigned as individual Nikkelverk refinery output.
Canada · Refined nickel · Operating system
Operator: Vale Base Metals
Production: 59,000 t · Period: 2025-01-01 — 2025-12-31 · Basis: Finished nickel, Site View · Operating-system scope
Source: Vale Base Metals 2025 Asset Handbook · 2026-03-30
Includes external and Manitoba feed; not Sudbury mine output.
Canada · Refined nickel · Operating system
Operator: Vale Base Metals
Production: 40,000 t · Period: 2025-01-01 — 2025-12-31 · Basis: Finished nickel, Site View · Operating-system scope
Source: Vale Base Metals 2025 Asset Handbook · 2026-03-30
Includes external feed; not Voisey mine output or standalone Long Harbour reporting.