Project background and reporting periods
Multiple annual reporting series are available; compare their product, ownership basis and reporting periods separately. The tables below keep each disclosure's own period and source; a later actual does not establish whether the original expectation was met. 2026-01-01 – 2026-12-31 · FY · full year
Compare the disclosures
Match the period, product, production boundary and ownership basis before subtracting. These examples retain the dates of the original disclosures.
Calculation checked on 2026-10-25 · Maintenance: MetalsGoWhere; update when the underlying disclosure changes.
What changed between the January and June 2025 ranges?
Guidance midpoint lowered 28.18%
Reference guidance
520–580 kt
Revised guidance
370–420 kt
0649.6 kt
2025 · Copper contained in concentrate · 100% project basis
Lower bound change
-150,000 t (-28.85%)
Upper bound change
-160,000 t (-27.59%)
Midpoint change
-155,000 t (-28.18%)
Check values, sources and calculation
Swipe horizontally to see the full table.
Reference
Value / disclosure date
Observation period / basis
Original source / location
Reference disclosure
520,000–580,000 t2025-01-08
2025-01-01 / 2025-12-31Copper contained in concentrate · 100% project basis
Recompute in tonnes. A midpoint is an arithmetic reference, not an issuer point forecast. Percentage changes use the corresponding reference value; a zero denominator has no percentage.
Do not use the mine-only annual actual to calculate a complex-guidance fulfilment delta. The January results release describes the revised range differently from the June revision; keep each dated disclosure and do not silently rewrite either historical range. No lost-tonnage estimate is inferred from disruption duration.
Are mine and complex totals the same production boundary?
No direct calculation
The product or production boundary differs; no conversion factor is assumed.
Check values, sources and calculation
Swipe horizontally to see the full table.
Reference
Value / disclosure date
Observation period / basis
Original source / location
Reference disclosure
385,808 t2026-01-15
2025-01-01 / 2025-12-31Copper contained in mine production · 100% project basis
Do not use the mine-only annual actual to calculate a complex-guidance fulfilment delta. The January results release describes the revised range differently from the June revision; keep each dated disclosure and do not silently rewrite either historical range. No lost-tonnage estimate is inferred from disruption duration.
Can concentrate and anode guidance form one unchanged series?
No direct calculation
The product or production boundary differs; no conversion factor is assumed. The observation periods do not match this calculation.
Check values, sources and calculation
Swipe horizontally to see the full table.
Reference
Value / disclosure date
Observation period / basis
Original source / location
Reference disclosure
370,000–420,000 t2025-06-11
2025-01-01 / 2025-12-31Copper contained in concentrate · 100% project basis
Do not use the mine-only annual actual to calculate a complex-guidance fulfilment delta. The January results release describes the revised range differently from the June revision; keep each dated disclosure and do not silently rewrite either historical range. No lost-tonnage estimate is inferred from disruption duration.
Cite this page with its project, observation period and calculation checked date. Historical examples do not establish today’s operating status or losses caused by an event.
Questions this evidence can answer
Checked: 2026-10-08 · Added: 2026-10-08
Why do Kamoa-Kakula annual output figures differ, and can guidance be compared directly?
Mine concentrator output excludes the slag concentrator, while the complex total includes it. Both are valid within their stated boundaries. Later saleable smelter output includes anode, blister and saleable slag concentrate; it should not be treated as an unchanged concentrate series.
Do not use the mine-only annual actual to calculate a complex-guidance fulfilment delta. The January results release describes the revised range differently from the June revision; keep each dated disclosure and do not silently rewrite either historical range. No lost-tonnage estimate is inferred from disruption duration.