Fiscal year vs calendar year in mining reports
As of 2026-10-21 · Observation periods are shown separately.
Mining companies report production for their own fiscal year. Many Australian-listed groups close their year on 30 June, so their 'FY2025' output covers July 2024 to June 2025; most other issuers and every USGS country table use the calendar year. A calendar-year figure and a June fiscal-year figure overlap by only six months and are not the same period. MetalsGoWhere keeps the exact period start and end on every record, so the examples below show the period before any comparison.
Definitions
Swipe horizontally to see the full table.
| Term | Meaning |
|---|---|
| Calendar year (CY) | 1 January to 31 December. Used by USGS, most government statistics and most Americas-, Europe- and Asia-listed miners. |
| June fiscal year (FY) | 1 July to 30 June, labelled by the year in which it ends (FY2025 = July 2024 to June 2025). Common among ASX-listed groups. |
| Other fiscal years | Some issuers end in March or September; Japanese fiscal years end on 31 March. The label alone never tells you the months. |
| Quarter labels | Q1 FY2025 for a June-year company is July to September 2024, not January to March 2025. |
| Period start / end | The dates MetalsGoWhere stores with every production record; the only safe key for alignment. |
Mechanical rules
Swipe horizontally to see the full table.
| If | Then |
|---|---|
| Two records carry the same year label. | Compare their period start and end dates, not the label; a match of label alone proves nothing. |
| A June fiscal-year figure must be placed against a calendar-year country total. | Show both periods explicitly and say they overlap by six months; do not rescale or average into a calendar year. |
| A company changes its fiscal year end. | Expect a transition period shorter or longer than twelve months; keep it as disclosed and never annualise it silently. |
Common misreadings
- '2025 production' from a June-year company is not calendar-2025 production.
- Adding four fiscal quarters gives the fiscal year, not the calendar year.
- USGS 2025e and a company FY2025 figure for the same country are not the same twelve months.
Examples from projects on this site
Records kept on their own basis: Each record keeps its disclosed product basis, ownership boundary and period; nothing is converted, summed or compared across bases on this page.
Swipe horizontally to see the full table.
| Record | Value | Unit | Data period | Basis | Ownership boundary |
|---|---|---|---|---|---|
| Kamoa-Kakula Reported actual Ivanhoe Mines | 385,808 | t | 2025-01-01 – 2025-12-31 · FY · full year | Copper contained in mine production | 100% project basis |
| Las Bambas Reported actual MMG | 410,834 | t | 2025-01-01 – 2025-12-31 · FY · full year | Copper contained in concentrate | 100% project basis |
Related research paths
Original sources and review evidence
- Ivanhoe Mines
Disclosure date: 2026-01-15
- MMG
Disclosure date: 2026-01-22
Updated: 2026-10-21
Standards and definitions cited
Definitions follow the documents below; check them for current versions. They are cited, not reproduced.
Follow the evidence
Source: metalsgowhere.com, as of 2026-10-21. Citation & data use